Maharashtra agrees to guarantee Dabhol loan from PFC

Hits smaller text tool iconmedium text tool iconlarger text tool icon
DabholThe Maharashtra government has offered some respite for the troubled Dabhol Power Project by agreeing to provide a guarantee for a Rs 300 crore loan that owner Ratnagiri Gas and Power Project Ltd (RGPPL) is seeking from the Power Finance Corporation (PFC).The revival of power generation from the plant is critical for Maharashtra, which is relying on Dabhol to bridge a 2,500 Mw monthly shortfall.

The 2,150 Mw plant has been operating below par since 2005 — generating 300 to 600 Mw — mainly owing to malfunctioning turbines, so the guarantee, which the state government had been reluctant to provide earlier, will mark a major step forward in restarting operations.

The loan guarantee is for two months, a senior RGPPL official said, because the company will be able to secure the loans on its own merit following a fuel supply agreement it expects to sign with Reliance Industries Ltd for gas from the Krishna-Godavari basin.

The loan will be used to repair the turbines that were supplied by General Electric (GE). The plant has three blocks with six gas turbines.

The cost of repair could be anywhere from Rs 50 crore to Rs 200 crore per turbine. There have been six major turbine failures since the revival of the plant in 2005.

Further comfort to lenders comes from the fact that GE has also agreed to start negotiations on the Comprehensive Service Agreement (CSA) for the equipment it has supplied to the plant.

Confirming the move, a senior Maharashtra government official close to the development said: “We have agreed to give the guarantee for two months to help them restore their capacity. Also, they are about to complete their gas supply agreement shortly.”

The official added that the guarantee offer needed central government approval and the state’s energy department was talking to the Union government for this.

Source - Business standard
 

Add comment


Security code
Refresh

Banner

Career Development Programs


Date: 26-09-2010
Topic: Pilferage of electricity- Legal & Technical aspects
Venue: Kalpetta , Wayanad
Faculty: Mr Madhu, EE, KSEB

Date: 03-10-2010
Topic: Enhancing managerial effectiveness
Venue: Malappuram
Faculty: Mrs Lizbeth Bose, Associate Professor, FIMS, Calicut & Mr Bose Jacob EE, KSEB

Follow us on Twitter

Reference Book

 

Reference Book on Power Vol-I

Electrical Engineering-- D' 1/4 Size Hard bound-- 1424 Pages-- Just Rs.1000/- only    ...

 

Reference Book on Power Vol-II

Civil Engineering & General-- D' 1/4 Size Hard bound-- 1144 Pages-- Just Rs.700/- only...

Registered Users

Total Members : 5704
Latest Member : cadsnegi
Today : 0 Registers
This Week : 10 Registers
This Month : 4 Registers

Visitor Statistics

mod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_counter
mod_vvisit_counterToday542
mod_vvisit_counterYesterday3172
mod_vvisit_counterThis week542
mod_vvisit_counterLast week16079
mod_vvisit_counterThis month8119
mod_vvisit_counterLast month69375
mod_vvisit_counterAll Days3184659

Visitors Online Now : 36
Your IP: 38.107.191.115
,
Today: Sep 04, 2010