KSEBOA - KSEB Officers' Association

Tuesday
Feb 09th
Text size
  • Increase font size
  • Default font size
  • Decrease font size
Home News Power Sector News Even after gestation period Dadri power project remains a non-starter

Even after gestation period Dadri power project remains a non-starter

smaller text tool iconmedium text tool iconlarger text tool icon
ADAGThe much publicised 10,000 mw gas-based Dadri Thermal Power Project of Anil Ambani is nowhere in site even after lapse of its gestation period of three years. But what has made UP to cut a sorry figure is the fact that the project, showcased as a great `power house' with a potential to ease the state's power shortage in one go, has virtually remained a non-starter. This is when the project was awarded with a breathtaking speed to Anil Ambani, also former Samajwadi Party (SP) MP to the Rajya Sabha and a member of the State Development Council headed by SP general secretary Amar Singh from 2003 to 2007.

The site for the project was chosen to be Dadri in Gautam Buddh Nagar, which is located in close proximity to Delhi in the National Capital Region. With a population of around 57,457, Dadri is not only known for its rich alluvial soil of Ganga-Yamuna doab, but also for high 84% literacy rate, which is much higher than the national average of 59.5%.

Its glorious past could be traced back to its proud history of its role in the uprising of 1857 when its Gujjar ruler Rao Umar Dedhar rose against the British rule and fought it bravely by roping in the support of other Gujjar rulers of the area. He was hanged along with four mutineers by the British.

Ambani's project was also in tune with Dadri's profile, as it is already a home to the NTPC's enterprises of 840 mw coal-based power plant and 830 mw gas-fired power plant. Two new units of 490 mw each are also coming up at the same plant. This plant has a switchyard with power handling capacity of more than 5000 mw. Besides, it has India's first biggest HVDC transmission line operating at 500 kv and handling power at 1,500 mw.

While no tenders were invited for the project, the Ambani group was virtually given an upper hand in the agreement. Under it, the state is entitled to only 40% of the power generated from the project whereas state has to bear 60% of the land cost.

The deadline set for its operation was 2008 as per the state support agreement (SSA) signed between the government and the Ambani's power company. It was also supposed to provide cheap power at the rate of Rs 2 per unit to power-starved UP.

For its tall promise, the company was rewarded amply with a huge 2,500 acres of most fertile land. This area is almost equivalent to that of the throbbing Gomti Nagar in the state capital, which accommodates sprawling dream projects of Mayawati and nearly one lakh houses, most of them quite palatial.

The huge chunk of land allocated for the project has always been debated on the floor of the Assembly. As per norms, the project of this magnitude could be set up on about 1000 acres of land.

However, ignoring this, then Mulayam Singh Yadav government pushed the project at a break-neck speed by choosing to acquire the land from farmers under section meant for `urgency' and defined only for the express purpose of public interest. In such a case, the purpose stated to be the commissioning of power project by the company, which never kept its promise.

Under the proceedings, coercive measures were also used in which around 500 FIRs were lodged against farmers. Those resisted acquisition of their land were even put behind bars. The hapless farmers were forced to accept the land compensations and signed a tripartite agreements between farmers, local administration and the company, said Rajpal Tyagi, president of Sahayoga Samiti of Farmers.

Insisting on his demand for cancellation of the project, Tyagi said that the project should be done away with immediately, as it had failed to meet the deadline. He said farmers were agitated and upset over acquisition of their land and would start a stir if denied justice. So far, he said, the farmers were in possession of their land and cultivating it under a Supreme Court order. For further hearing, he said, the apex court had referred the matter to the Allahabad High Court, which had currently reserved its judgment on the issue after a prolonged hearing.

Source - Times of India
Comments (0)Add Comment
Write comment
 
  smaller | bigger
 

security image
Write the displayed characters


busy
 
Follow us on Twitter
Banner
Latest Downloads
KSEBOA News Magazine January 2010
KSEBOA News Magazine December 2009
Free Software for preparation of Income Tax statement, ITR for 2009-10 for senior citizens
THE FOLLOWING TRAN. AND POSTINGS OF AEE(E) DTD.31.12.09
CORR. IN THE PRO. AND POST. OF AE(E) TO AEE(E) DTD.31.12.09
PRO. AND POST. OF AEE(E) TO EE(E) AND TRA.EE(E) DTD.30.12.09
Pro. and Posting. of EE(E) to DYCE(E) dtd.11.12.2009
TRANSFER AND POSTINGS OF AEE(E) ORDER DTD.08.12.2009
KSEB Promotions of AE(Ele) to AEE(Ele) Degree Quota dated 08-12-2009
KSEB Promotions of AE(Ele) to AEE(Ele) Diploma Quota dated 08-12-2009
KSEBOA News Magazine November 2009
Convert numeric value to English words for MS Excel and Open office calc
KSEBOA News Magazine October 2009
KSEBOA News Magazine September 2009
Retirement of KSEB employees- Implementation Order Dated 22-09-2009
Latest News
Popular Downloads
Study report on LT Billing computerisation in KSEB 4767
Power Quiz Sample Questions 4159
Free Software for preparation of Income Tax statement, Form-16, ITR-1, ITR-2 for 2009-10 3191
Free Software for preparation of Income Tax statement for 2008-09 2506
Study report on Power sector private participation in Kerala 1690
KSEB General Transfer - Application format for officers 1676
Software for preparation of CTC 1500
Free Software for preparation of MASA 1328
Free Software for preparation of work bills 1143
Free Software for Preparation of Estimates using Open office 1067
KSEB Transfer Scheme - Kerala Gazette Notification No-2090 Dated 25-09-2008 1016
Free Software for 11KV Voltage regulation calculation and preparation of VR chart 956
CUG Mobile Telephone Numbers of KSEB Offices/ Officers 921
Traiff for retail supply by KSEB wef 01-12-2007 638
PSC Rank List of AE(Ele) including addentum dated 07-07-2009 629
Popular News
Malayalam News
Breaking News
Videos

Reference Book

 

Reference Book on Power Vol-I

Electrical Engineering-- D' 1/4 Size Hard bound-- 1424 Pages-- Just Rs.1000/- only    ...

 

Reference Book on Power Vol-II

Civil Engineering & General-- D' 1/4 Size Hard bound-- 1144 Pages-- Just Rs.700/- only...

Registered Users

Total Members : 4812
Latest Member : shamla
Today : 1 Registers
This Week : 7 Registers
This Month : 25 Registers

Visitor Statistics

mod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_counter
mod_vvisit_counterToday1118
mod_vvisit_counterYesterday2225
mod_vvisit_counterThis week5251
mod_vvisit_counterLast week16495
mod_vvisit_counterThis month19462
mod_vvisit_counterLast month71034
mod_vvisit_counterAll Days2365286

Visitors Online Now : 51
Your IP: 38.107.191.85
,
Today: Feb 09, 2010