Category |
Range in kWh |
Type of
supply |
Unit |
Energy charge
/KWH in Paise |
|
LT-I(a) |
0-40 |
|
Ps/unit |
115 |
|
41-80 |
|
Ps/unit |
190 |
|
81-120 |
|
Ps/unit |
240 |
|
121-150 |
|
Ps/unit |
300 |
|
151-200 |
|
Ps/unit |
365 |
|
201-300 |
|
Ps/unit |
430 |
|
301-500 |
|
Ps/unit |
530 |
|
Above500 |
|
Ps/unit |
545 |
|
Tariff minimum
payable
other than during the
period of disconnection |
Single Phase |
Rs / month |
30+ 2.50
(Duty) |
|
Three Phase |
Rs / month |
170 + 12.50
(Duty) |
|
Tariff minimum
payable
during the period of
disconnection |
Single Phase |
Rs / month |
30 |
|
Three Phase |
Rs / month |
60 |
|
LT-I(b) |
0-40 |
|
Ps/unit |
155 |
|
41-80 |
|
Ps/unit |
240 |
|
81-120 |
|
Ps/unit |
280 |
|
121-150 |
|
Ps/unit |
345 |
|
151-200 |
|
Ps/unit |
405 |
|
201-300 |
|
Ps/unit |
505 |
|
Above 300 |
|
Ps/unit |
630 |
|
Tariff minimum
payable
other than during
the period of disconnection |
Single Phase |
Rs/ month |
40+ 3.00
(Duty) |
|
Three Phase |
Rs/ month |
205 + 17.00
(Duty) |
|
Tariff minimum
payable
during the period
of disconnection |
Single Phase |
Rs/ month |
40 |
|
Three Phase |
Rs/ month |
80 |
|
LT-II |
Fixed Charge
|
|
Rs/ month |
1990 |
|
Energy Charge |
|
Ps/unit |
565 |
|
LT-III |
Energy
Charge or |
|
Ps/unit |
1350 |
|
Daily Minimum
|
|
Rs./ kW or
part
thereof of
connected load |
135 |
|
LT-IV |
Fixed Charge |
|
Rs/ kW or
part
thereof connected
load /month |
45 |
|
Energy Charge |
|
Ps/unit |
325 |
|
LT-V |
Fixed Charge |
|
Rs/ kW /month |
6 |
|
Energy Charge |
|
Ps/unit |
65 |
|
LT-VI (A) |
Fixed Charge |
|
Rs/ kW /month |
40 |
|
Energy Charge |
Up to 500
Units |
Ps/unit |
385 |
|
|
Above 500
Units |
Ps/unit |
520 |
|
LT-VI (B) |
Fixed Charge |
|
Rs/ kW /month |
55 |
|
Energy Charge
|
Up to 500
Units |
Ps/unit |
450 |
|
|
Above 500
Units |
Ps/unit |
590 |
|
LT-VI (C) |
Fixed Charge |
|
Rs/ kW /month |
170 |
|
Energy Charge |
Up to 500
Units |
Ps/unit |
675 |
|
|
Above 500
Units |
Ps/unit |
860 |
|
LT-VI (D) |
Fixed Charge |
|
|
NIL |
|
Energy Charge |
Up to 100
Units |
Ps/unit |
75 |
|
|
Above 100
Units |
Ps/unit |
85 |
|
Tariff minimum
payable
during the period of
disconnection and
Non-disconnection |
Single Phase |
Rs/ month |
15 + 1.00
(Duty) |
|
Three Phase |
Rs/ month |
25 + 2.00
(Duty) |
|
LT-VII (A) |
Fixed Charge |
Single Phase |
Rs/ kW or
part thereof /month |
50 |
|
|
Three Phase |
Rs/ kW or
part thereof /month |
100 |
|
Energy Charge |
Upto 100
Units |
Ps/unit |
565 |
|
|
Upto 200
Units |
Ps/unit |
625 |
|
|
Upto 300
Units |
Ps/unit |
695 |
|
|
Upto 500
Units |
Ps/unit |
750 |
|
|
Above 500
Units |
Ps/unit |
825 |
|
LT-VII (B) |
Fixed Charge |
|
Rs/ month |
30 |
|
Energy Charge |
Upto 100
Units |
Ps/unit |
350 |
|
|
Above 100
Units |
Ps/unit |
540 |
|
LT-VII (C)
|
Fixed Charge |
|
Rs/ kW or
part thereof /month |
80 |
|
Energy Charge |
Upto 1000
Units |
Ps/unit |
440 |
|
|
Above 1000
Units |
Ps/unit |
590 |
|
LT-VII (D) |
Fixed Charge |
|
Rs/ kW or
part thereof /month |
Tariff as
per
LT-VII (A) |
|
Energy Charge |
Upto 100
Units |
Ps/unit |
|
|
Upto 200
Units |
Ps/unit |
|
|
Above 200
Units |
Ps/unit |
|
LT-VIII |
Fixed Charge |
|
Rs/ kW or
part thereof
connected load
/ day |
50 |